Windows installed; air conditioning and electric being run.

  • It’s been six months since we said “yes build this house please”.
  • This is Build month #4 quickly coming to a close.
  • I can’t think of anything else useful to outline here, so let’s get to the photos.

So here was work going on at the home site on this past Sunday, as such we couldn’t really get in there until everyone was gone.

It was raining too, so we were in and out.  (Muddy outside with the dirt and all)  This made the house look crappy in the dull light, so I didn’t take many exterior pictures this trip…sorry.

^ Two views from the upstairs windows looking across the street from front of home.

^ A/C duct work and general “mess” going on in the Game Room area as things inside start taking shape.

^ Emzy came with us, yeah.  This is the duct work going in behind the Garage wall area.

^ This seems to be the “list of things to correct” as scribbled onto the garage wall.  Kind of interesting.

Seems the plumbing work passed inspection, so the A/C lines are going in, along with some electrical, but not much to report otherwise.

Biggest surprise was the home’s windows have all been installed!

 

You’d think we were in the home stretch (ha, bad pun) but we’re going to have to wait for electrical to be finished, walls, flooring, paint… and who knows how many more inspections… (since the windows have gone in).  We’re also hoping some of the leaks we saw yesterday are because some structural stuff just hasn’t all been completed yet — and if so, they get it wrapped up soon!

As we figured, our closing date has been re-adjusted.. finally.    We’re now anticipating a closing around 3/31.  Two months behind schedule.  3/31 isn’t even a weekday though, so we’re going to try to get a better date scheduled.

More details here once we get it all figured out ourselves.

~Byron